Click Here to Print Select Font Size: A A A
Sponsored By
India May Resuscitate Disputed Enron Plant
By Vir Singh

Nothing quite captures India's dilemmas like the sorry tale of the Dabhol power plant. Built by an Enron-led consortium near Mumbai (Bombay) in the 1990s, Dabhol briefly produced power for the grid, only to languish after local authorities and the multinational company came to an impasse over electricity pricing five years ago. Fast-growing but energy-poor, India desperately needed and still needs the power the plant would have provided. Yet local politicians, eager as ever to promise their constituents below-market electricity prices and, if possible, line their own pockets in the process, played on Indians' traditional deep hostility toward foreign investment.

That, anyway, is pretty much how international investors have seen the situation. But from India's perspective, to the contrary, it was a tale of how the country, yet again, had been victimized by a predatory globalizing corporation. From the outset, respected critics warned that the plant and its electricity would be too expensive, and circumstances strongly suggested that the project would not have proceeded without money's changing hands under the table [see sidebar,

 
Months after Dabhol was turned off in 2000 [see photo,

Photo: Arko Datta/Reuters

Shuttered: The Dabhol power plant, nearly complete and already producing electricity, was closed down five years ago when Enron and the local government came to an impasse over electricity pricing.


 
], Enron's corporate leadership in Houston stood exposed, if not as an outright criminal conspiracy, then at least as seriously short on scruples.

This summer, however, an unprecedented power crisis in India's western state of Maharashtra, home of the Dabhol facility, has prompted fresh talks to complete and turn on the 2184-megawatt power plant. The improved prospects for Dabhol, in turn, are awakening hopes that India's entire power industry may finally change for the better as it is reorganized to respect market principles and encourage new technology. As India's largest foreign investment, Dabhol was the icon for a more friendly attitude toward outside capital after the national government adopted market-oriented economic reforms in 1991.

Until recently, General Electric Co., in Fairfield, Conn., and the U.S. engineering firm Bechtel Corp., in San Francisco, owned just over 85 percent of the US $2.9 billion plant, having taken over Enron's 65 percent stake. But at the end of June, GE said it had agreed to sell its share to a group of financial institutions. GE is expected, however, to stay on the Dabhol project as a contractor—and Bechtel may as well [see photo,

Photo: Savita Kirloskar/Reuters

Ready To Go: The Dabhol plant, if completed, would have the capacity to produce nearly 2200 megawatts of electricity from natural gas, which would be delivered in liquefied form.


 

With the Indian state-owned firms National Thermal Power Corp. and Bharat Heavy Electricals Ltd., GE has been devising a plan to start a smaller unit at Dabhol and then complete the rest of the project.

"GE is pleased with the course of discussions with the various stakeholders [in Dabhol] and looks forward to a complete resolution of the outstanding issues," said Scott Bayman, president and chief executive officer of GE India, in a written statement.

There are good reasons for GE's optimism about the state government's intentions. This spring and summer, power cuts of up to 4 hours in midsize towns and as much as 9 hours in rural areas provoked angry mobs to stone the offices of the Maharashtra state electricity board (SEB), as terrified officials locked themselves in. Even outlying suburbs of India's financial capital were hit by brownouts.

With popular pressure mounting to provide more reliable electricity, the state board's posture toward Dabhol has softened. Attitudes also are changing in New Delhi. Two years ago, the federal government enacted an electricity reform law designed to introduce more competition and flexibility into the system, and that change in philosophy is starting to make itself felt in the provinces as well. "There is a very clear understanding and recognition [among SEBs] of the fact that they need to move toward a market model," in which prices would be set by free markets rather than by board regulators, says Gaurav Bhatiani, who has worked as a consultant to the U.S. Agency for International Development on India's power distribution reforms. "Earlier, four to five years back, they would have laughed if you had said they [needed] competition."

Indian consumers, many of whom have to purchase backup power because the grid is so unreliable, may be getting more realistic, too, about what it will take to make the system work better. "Nobody expects that the prices will automatically fall" with electricity reform, says Kottilil Ramanathan, a senior fellow at the Energy and Resources Institute, in New Delhi. What's wanted most, he believes, is "better supply and service."

Still, there is a long way to go. Politicians consider SEBs their personal fiefdoms—vehicles for giving heavily subsidized or free electricity to farmers and other powerful groups. In large states such as Uttar Pradesh, Bihar, Punjab, Rajasthan, and Maharashtra, officials openly use the government-run distribution companies to win political support. The SEBs in such states routinely operate at a loss, not only because of the electricity they subsidize but also because of brazen theft. Often users simply attach a cable to overhead power lines, preferring to pay bribes rather than deal with the hassle of formally applying for a metered electricity connection.

Maharashtra's current power crisis has forced political parties to rally behind Dabhol. The plant could be producing 740 MW in its first phase by the middle of next year.

But state officials still maintain that the plant can and must supply power to the distribution companies at about 5 cents per kilowatthour, instead of at the much higher rates originally negotiated. If the perception takes hold that the SEB will not shake its habit of selling electricity at a loss, the impact on foreign investors will be unfortunate.

Just the same, consultant Bhatiani feels that India's moves to end the virtual monopoly of the SEBs are a good signal to potential investors. "The market is huge," he says, because per capita electricity consumption in India is nowhere near the level in other Asian countries. Average annual personal consumption is about 500 kWh, compared with more than 900 kWh in China and nearly 9000 kWh in the United States. With an installed capacity of 112 000 MW, India has set its sights on adding 100 000 MW by 2012.

Eyeing that market, GE's chairman and chief executive officer, Jeffrey R. Immelt, met with Prime Minister Manmohan Singh and other top Indian ministers during a visit in May. Referring to Dabhol, Immelt said, "We are very keen to put people on the ground very quickly."

—Vir Singh




Sidebar 1

The Dabhol Tangle

1992

Houston's Enron corp. and the west central Indian state of Maharashta agree to build a large gas-fired power plant in Dabhol, near Mumbai (Bombay). The project leads to the formation of the Dabhol Power co., a joint venture of Enron, General Electric, and Bechtel. Enron takes a 65 percent stake.

1993

The Central Electricity Authority in New Delhi approves in principle the construction of the Dabhol plant at an estimated US $3 billion, the largest private foreign investment in India's history. The World Bank reports the plant is too big for the state's needs and that electricity from it will be too expensive.

1994

The U.S. Export-Import Bank and the Overseas Private Investment Corp. approve $600 million in loans and guarantees for Dabhol.

1995

An electoral coalition opposing the Dabhol project wins the state election in Maharashtra and takes office. A committee appointed by India's federal government finds that the project's capital costs have been inflated and that electricity prices will be too high. Nevertheless, the new state government renegotiates the project, making it three times bigger and agreeing to terms that critics consider scandalously favorable to Enron, giving rise to suspicions that corruption played a role.

1999

the first phase of the plant (740 megawatts) starts operation. Human Rights Watch reports that local activists, opposing the project have been abused by security forces paid by the state electricity board.

2000

Influential citizens call on the Maharashtra government to terminate purchases of electricity from the plant on the grounds that it is too expensive.

2001

En declares bankruptcy. Dabhol electricity is found to cost 4 times as much as electricity from other sources in Maharashtra. The operation of Phase I of the plant is stopped; construction of Phase II (1444 MW), 90 percent complete, is halted.

2004

The newly elected Congress Party government in New Delhi reaffirms its commitment to the national policies of economic liberalization.

2005

Increasingly severe power shortages add urgency to the resuscitation of Dabhol.