Officials at CERN, near Geneva, believe they have
found a solution to the latest hitch in the construction
of the Large Hadron Collider (LHC), a state-of-the-art
particle accelerator that straddles the Franco-Swiss
border. That was the upshot of a two-day review held the
last week of April at CERN to find a way forward
following a major failure during a high-pressure test on
critical components of the machine in March. The
mishap casts a pall on a situation that otherwise
seemed to be all-systems-go.
The LHC is a 27-kilometer-long circular tunnel
designed to collide proton beams. Scientists hope that
the products of those collisions will lead to better
understanding of matter and the universe. The beams are
directed through the tunnels by 1700 superconducting
magnet assemblies, and it was a small but important
subset of these—roughly eight 35-meter-long linear
assemblies of focusing magnets called inner
triplets—that ran into trouble.
The test was intended to simulate the kinds of forces
the magnets will encounter under actual operating
conditions and to examine, for instance, the movements
of pipes. Pressure was applied to one of the triplet
assemblies in steps of 5 bar, says Ranko Ostojic, a CERN
engineer who leads the team responsible for the LHC’s
special-purpose magnets. On the night of the test,
Ostojic was in the tunnel with seven other people,
making measurements. At 12 bar, the observers retreated
30 meters from the magnet, in keeping with safety rules.
At 20 bar, there was a sudden release of helium gas
(used to cool the magnets), something went bang, and
sirens sounded, alerting the fire brigade. No one was hurt.
Examination half an hour later showed that the
magnets were basically in good order. But the pipes
connecting them were another matter. Some had shifted a
little, some a lot, and one had fractured, which is what
caused the discharge of helium gas. Moreover, the
supports for one of the magnets, glass-reinforced plastic
structures called spiders, had broken.
Post-mortem analysis showed that the supports weren’t
strong enough to counteract an asymmetric longitudinal
force of about 15 tons.
Fermi National Accelerator Laboratory, in Batavia,
Ill., the U.S. national laboratory, along with two other
U.S. facilities and the High Energy Accelerator Research
Organization, KEK, in Japan, designed the triplet
magnets and supplied them to CERN. Fermilab announced
the failure and immediately accepted blame for what it
calls a design blooper. But the lab is hard put to
explain how the problem happened. It isn’t that the
forces were unknown, says James Kerby, U.S. LHC
accelerator project manager at Fermilab. “We’re aware of
them, and we didn’t properly account for them.” Four
external design reviews carried out from 1998 to 2002
also failed to detect the flaw.
The magnets have suffered other, minor mishaps. Some
of the initial supports arrived in Geneva damaged,
after having been transported by train,
which was in direct violation of
shipping instructions. And in December,
another pressure test resulted in the collapse of heat
exchangers in the triplets. Both defects have been
rectified, says Kerby, and neither had anything to do
with the current issue.
Fermilab successfully tested the magnet elements
separately before sending them to Switzerland. But the
forces that caused the failure could occur only in the
collective behavior of several magnets strung together,
as they were in the tunnel. In addition to pledging its
full support to CERN, Fermilab is conducting its own
series of reviews “to fix the process” that led to the
oversight, says Kerby, “until we get it right.” The
purpose of last week’s meeting, however, was solely to
remedy the problem at hand.
A total of nine units (eight commissioned, and one
spare) need to be “upgraded.” Although only one unit of
three magnets was involved the March incident, says
Ostojic, “it’s a systematic problem.” The fix will
reinforce the magnets at critical points with
“cartridges,” stiff mechanical springs made of invar (a
type of steel) and aluminum. Broken spiders will be
replaced, but otherwise need no redesign. Both the
cartridge alone and cartridge plus magnet will be tested
on the surface at appropriate loads. It is hoped that
the magnets inside the tunnel can then be modified
without having to be brought to the surface.
That will save time, though it looks increasingly
unlikely that CERN will meet its deadline for an
engineering run at the end of 2007. People are
philosophical about the episode, citing the LHC’s
enormous complexity. What is annoying is to have it
happen at such a late stage. “We will see now how
quickly we can recover from this,” says Lyn Evans, LHC
project director. “Our real number one priority is to
make sure…that we come online as foreseen in spring
2008, and that we get the machine up to top energy as
fast as we can. With or without an engineering run
before.”