Illustration: BRYAN CHRISTIE DESIGN
|
Mumbai’s peak load of about 2600 megawatts now
substantially exceeds local generation capacity,
which is only 2277 MW.
|
Five major grids—located in the north, east,
northeast, west, and south—serve India. Except for the
southern grid, all the others, totaling more than 100
000 MW in generation capacity, are on a synchronous tie,
meaning that they are interconnected and share a common
system frequency. Maharashtra state, of which Mumbai is
the capital, is part of the western grid, which also
includes the states of Gujarat, Madhya Pradesh,
Chattisgarh, and Goa, an area of 11 million square
kilometers with an installed capacity of around 47 000
MW.
Because Mumbai is connected to the western grid and
receives some electricity to meet peak demand from the
Maharashtra State Electricity Transmission Co., the
city’s load directly affects conditions elsewhere in the
state. Mumbai’s peak load of about 2600 MW now
substantially exceeds local generation capacity, which
is only 2277 MW. Tata provides 1777 MW to its direct
customers, which include the commuter railway and heavy
industry and whose peak load is about 500 MW. Tata also
supplies the Brihanmumbai Electric Supply &
Transport Undertaking (BEST), a public company that runs
the city’s bus system and that distributes power to the
southern portion of Mumbai. BEST’s customers’ peak load
is about 800 MW. Reliance Energy, Mumbai’s other major
utility, which supplies the northern half of the city,
also buys electricity from Tata to supplement its own
500 MW of generation and meet its customers’ peak load
of 1300 MW. To make up the shortfall, Tata often
purchases power from the state of Maharashtra, for which
the company pays an annual standby fee of $94 million
on top of the actual cost of the electricity it imports.
Peak demand in Maharashtra, about 17 000 MW, exceeds
generation capacity by about 5000 MW. That means planned
load shedding goes on every day in parts of Maharashtra,
where many rural areas have power for only 10 hours.
Such privations are a fact of daily life that most
Indians outside Mumbai have learned to live with and
plan for, like the monsoons.
Increasing the availability, reliability, and quality
of electricity is a long-term goal that will be met only
with tens of thousands more megawatts of generation
capacity. In the near term, administrators and engineers
from both Mumbai power companies, Tata and Reliance,
along with officials from the Maharashtra Electricity
Regulatory Commission, are doing their best to stave off
planned load shedding and avoid a catastrophic blackout
that could cost the local economy billions of rupees.
Blackouts occur when load so far outstrips generation,
either because of the loss of a generator or a major
transmission line, that the frequency dips to 47.5 Hz.
At that point, the generators automatically trip off and
a blackout ensues. For example, on 25 February India’s
western grid went down, and the citizens of Maharashtra
were without power for several hours.
But as always, Mumbai was mostly spared. Both Tata and
Reliance invoked “islanding” schemes, whereby they take
the city off the national grid and supply customers with
power from their own local plants until the larger
network comes back up. First deployed by Tata in the
late 1960s, the separation happens only when the
integrity of the system cannot be maintained despite
automatic emergency load shedding. The islanding does
not require centralized computer control. Instead,
reverse-power and underfrequency relays sense that the
system frequency has dipped to 47.6 Hz and independently
trip breakers on the six power lines that connect Tata
and Reliance with the regional grid.
Most times the Tata and Reliance systems survive
together as one island, but occasionally Reliance
separates into an independent grid, as happened this
past February. On that day, Tata generation was low due
to the outage of a 500-MW coal-fired generator and a
150-MW gas turbine. According to K. Rajamani, chief
consultant for Reliance, the utility had been importing
electricity from Tata over tie lines with a capacity of
30 MW. That same day, a problem with a 400-kilovolt
transmission line located near Mumbai destabilized the
grid.
When system frequency dipped to 47.6 Hz, Tata and
Reliance separated from the sinking western grid. Under
normal conditions, power flows from Tata to Reliance
over the interconnecting tie lines. But on 25 February,
the problem with the western grid, coupled with
generation deficiency in the Tata system, created a huge
power swing that reversed the normal flow of electricity
from Tata to Reliance.
The reverse-power condition fooled the load-shedding
logic in Reliance’s Supervisory Control And Data
Acquisition (SCADA) system, which is based on importing
power from Tata. As a result, the SCADA system did not
initiate automatic load shedding, and the Reliance
generators fed Tata loads. This led to a steep decline
in frequency, which tripped the generators at Reliance’s
500-MW plant at Dahanu and shut off power to about 1.7
million customers for 1 to 4 hours. Once Reliance’s
system began to fail, Tata became its own island within
an island. Despite its lower-than-normal generating
capacity, Tata managed to keep the lights on in the
southern part of the city served by its customer BEST,
the 14th time it has islanded successfully since the
last citywide blackout in 1997.
Mumbai’s dramatic increases in load over the past five
years—averaging 5 percent annually—have strained the
existing power
system to the breaking point. Only a small
part of that growth can be attributed to the influx of
perhaps 1000 immigrants a day, most of whom are
destined to sleep on the footpaths or seek shelter in
the slums. Some of the recent demand comes from new air
conditioners and washing machines, purchases enabled by
a robust national economy, which expanded at a rate of
8.5 percent last year. And then there is the building
boom. Much like Manhattan, Mumbai can only accommodate a
swelling and increasingly affluent population by going
vertical. Everywhere you look you see tower cranes
helping buildings shoulder their way into the skyline.
In addition, the mass conversion of 243 hectares of old
textile mills in the heart of the city into commercial
and residential space is creating glitzy, fully
air-conditioned malls that rival the suburban temples of
consumption found all over the United States. Add it up
and it’s no wonder that the power companies, which have
not built a new plant in a decade, are scrambling to
keep the lights on.