WASHINGTON
A study of U.S. electricity transmission needs, done
by an expert team under the auspices of the U.S.
Department of Energy (DOE), should be released roughly
as this issue goes to press and will be available online
[see "To Probe Further," below]. Organized like DOE's
Post-Outage Study Team (POST), which examined the summer
1999 power failures [see "Restructuring the
Thin-Stretched Grid," IEEE Spectrum, June 2000, pp.
43-49], the National Transmission Grid Study was
launched last August but got going in earnest only after
11 September.
Because of the attacks, the three public hearings
held around the country in late September may have been
less eagerly attended than hoped, and participants may
have been distracted. Certainly, infrastructure security
moved higher up the agenda, and transmission congestion
may not have come in for quite the priority concern
expected.
In any event, the study team did its final work at a
time when other key authorities were sounding many
alarms about transmission. The North American Electric
Reliability Council, the power industry's
self-regulation organization based in Princeton, N.J.,
has said the nation "is at a crisis stage with respect
to the reliability of transmission grids." In short,
transmission lines in many parts of the United States
are in danger of becoming overloaded and failing.
Issues other than reliability matter, too. The
Federal Energy Regulatory Commission (FERC), already
more aggressive under its new activist chairman and Bush
confidant Pat Wood, issued a preliminary Transmission
Constraint Study on 19 December. Chokepoints identified
in the document increase costs to customers as well as
undermining system reliability.
Focusing on events of the summers of 2000 and 2001,
the FERC study group sought to evaluate effects of
congestion—more current trying to pass a point in the
transmission system than that point can handle—to
demonstrate costs to consumers and stir policy
discussion.
Congestion costs were calculated by looking at the
uncongested and congested sides of transmission choke
points, multiplying the price difference by the energy
transmitted across the bottleneck, and adding the cost
of the extra energy produced on the congested side to
replace whatever was blocked by the bottleneck. The FERC
group then listed and aggregated those costs [see table
below].
The conclusion: congestion had cost consumers an
extra US $1 billion and more during those two summers
alone. Fixing 16 bottlenecks by adding transmission
would cost $12.6 billion, in the group's estimate, but
the upgrade would pay for itself in just a few years.
Extra fees to consumers to pay for upgrades would be
almost imperceptible in monthly bills.
Also in December, but separately, the power
industry's Edison Electric Institute (EEI), Washington,
D.C., issued transmission-related studies drawing
attention to several key issues and issue areas. Winning
local, state, and federal approvals was found to be the
biggest single obstacle to adding transmission capacity.
Transmission in the western United States was found to
be especially wanting.
In testimony to Congress on 10 October, EEI had said,
"Annual investment in transmission has been declining by
almost $120 million a year for the past 25 years. ...in
1999 [it] was less than half of what it had been 20
years earlier."