With additional
reporting on sidebars by Willie D. Jones, Elizabeth
A. Bretz, and Chris Lang
21 August 2003—What was by most measures the biggest
electricity outage in history, surpassing the blackouts
in the western United States in the summer of 1996,
swept northeastern and Great Lakes states and the
Canadian province of Ontario late Thursday afternoon, 14
August. Long before power had been restored to
businesses and residences from New York City to
Cleveland, Detroit, and Toronto, politicians and
commentators on both sides of the border were pointing
fingers. But, in fact, major difficulties in the
electric power system had been predicted by three U.S.
Department of Energy (DOE) studies going back to 1998,
and had been duly reported in the press (including
IEEE
Spectrum), with plenty of blame for inaction
to go all around.
At this writing, it appears that the 2003 blackout
started in facilities owned and operated by FirstEnergy
Corp., a large utility headquartered in Akron, Ohio.
Early in the afternoon of 14 August, one of its
coal-fired power plants began to behave oddly and had to
be taken off-line, or "tripped" in the industry parlance
[see Timeline].
An hour later and perhaps coincidentally, at 3:06 p.m.,
Eastern Daylight Time, one of the company's major
transmission lines failed. Inexplicably, the alarm
system meant to warn the utility of such problems did
not operate properly, and so FirstEnergy did not give
regional regulators and organizations in adjacent states
any warning of the mishap.
Over the next 45 minutes, three more transmission
lines failed—two owned by FirstEnergy, the other by
American Electric Power (Columbus), the other big Ohio
utility—at 3:32, 3:41, and 3:46 p.m. By 4:30 p.m., most
people in Ohio, Michigan, Ontario, New York State, New
Jersey, and Connecticut were without power.
In the coming weeks and months, as regulators and
power engineers sift through thousands of event records,
the focus initially will be on what exactly the
initiating events were, why failures propagated so
rapidly through the northeastern grid, and why the grid
system operators established to prevent such disasters
were unable to deliver. Initially, responsbility for the
inquiry was taken by the North American Electric
Reliability Council (NERC, Princeton, N.J.), the
self-regulating utility organization meant to improve
the trustworthiness of the grid
system, and it will continue to provide data
and analysis. NERC's leaders have let it be known that
an objective will be to determine whether key
players failed to follow rules properly or
whether the rules themselves were defective.
"We were all just waiting for the big one."
Ultimately, however, the issues raised by the
blackout go far beyond that, which may be why DOE took
charge of the inquriy on 20 August. For more than five
years, NERC has sought and failed to get legislative
authority to make its rules mandatory. During the same
period, its U.S. government counterpart, the Federal
Energy Regulatory Commission (FERC, Washington, D.C.),
has been struggling to impose stronger regional
oversight over grid operations—often encountering
impassioned opposition from big utilities and their
political allies. (FERC deals mainly with state and
local governments, NERC with utilities.) Meanwhile, as
growth in demand for electricity has outstripped
additions to transmission capacity by a factor of two,
the grid itself has come to be ever more thinly stretched.
The net result, as virtually all experts on the
nation's grid system came to agree, was a disaster
waiting to happen. "We all knew something like this was
coming along," a leader in a 1999 DOE study of the
transmission grid told IEEE Spectrum, on condition of
anonymity. "We were all just waiting for the big one."
"Look," agreed Karl Stahlkopf, an executive at Hawaii
Electric Co. (Honolulu) who previously managed power
system research at the Electric Power Research Institute
(Palo Alto), "everybody in the business knew something
like this was going to happen. It wasn't a question of
whether but when."